Inspired is currently overseeing phases 2 and 3 of a refurbishment of 28 blocks of two storey accommodation buildings containing 240 units of 2 berth residential accommodation, which provide temporary self-catering accommodation for 480 members of the resorts resident seasonal operational team.
Condition reporting along with bespoke refurbishment technical design including exterior landscaping adjustment, exterior and interior finishes were all provided by Inspired, cost advise and a competitive tender process involving 5 principal contractors saw final negotiation with two contractors, whom are now providing a concurrent program of Fast track delivery under live contracts. JCT form contracts are Administered by Inspired, whom also act as Project Managers to coordinate all parties through the holding of regular site meetings and the undertaking of frequent site inspections assessing quality and valuation.
Inspections for assurance of compliance with the clients specification and a high quality of finishing’s are overseen and continually assessed, along with a phased hand-over by Inspired of course working in close conjunction with the Principal Contractors and the resorts personnel management team, the newly occupied units are receiving exceptionally positive feedback, to the credit of all parties involved in the process.
The project is due to be completed by the end of March 2020, and the works are currently on program to be fully delivered exactly as anticipated.