Inspired were appointed by our longstanding client to support their project team with concept, coordination, and implementation design packages for the replacement of finishes, the provision of new Performer facilities, and the replacement of a Full Discharge wet sprinkler system in one of the Primary Entertainment venues, at their UK leisure holiday park in Somerset.

Our Project Managers, Quantity Surveyors, and Technical Design team have collaborated tirelessly to coordinate the delivery of concept, technical design, cost planning & commercial management services for our client in relating to the provision of new services and facilities within a 3000-seater Auditorium, together with bars, shops, and servicing spaces covering a combined area of 50,600 sqft on one floor.

Our clients’ proposals include the replacement of ALL backstage dressing room and welfare facilities, all stage & production offices and working spaces, together with the enhancement of storage and servicing spaces including mezzanine structures, costume washing facilities, and a general enhancement of performer and crew movement strategies. The project will see a new Sprinkler system installed due to the risk profile of the premises along with a new exterior reservoir, the replacement of all internal ceilings, all associated accommodation and emergency lighting systems necessary to afford access, also the renewal of all specialist stage sound and lighting installations for the purpose of future proofing. Equality measures will also be renewed ensuring that all areas are accessible to guests and performers, and the venues entrance and front of house areas will see new brand and marketing finishes installed, in all creating a new feeling of bright & fresh for their guests.

Our clients appointed Principal Contractors at Jones Building Group are currently 12 weeks into a 53-week contract, commencing initially on 30 October 2023 the project has been carefully planned out using a combination of daytime and night shift working patterns to accommodate the venues status as a live entertainment venue, the works are programmed for completion in October of 2024 in good time for winter festivities to commence. Electrical consultancy has been provided by ME Engineers, and Structural engineering designs provided by a team of engineers from Crouch Waterfall.

If you require assistance with the technical design and management of your project, in any sector, call Inspired on 01823 270764 or email us at info@inspired-partnership.com with your bespoke services enquiry.